Etruscan Resources



The Mine

The mine commenced production in February, 2008 and commercial production and substantial completion of construction was effective on July 1, 2008. Gold production for fiscal 2008 which comprises the five months of commercial production ended November 30, 2008 aggregated 29,305 ounces at an estimated cash operating cost of US$598 per ounce. The initial open pit mining operation is comprised of five pits with the ore being processed over an initial 6.6 year mine life through a conventional gravity-CIL (carbon-in-leach) plant with a design capacity of one million tonnes per annum.

Location

The Youga Gold Mine is located approximately four kilometers north of the Ghanaian border and 180 kilometers southeast of Ouagadougou, the capital city of Burkina Faso on the 80 kilometer Youga Gold Belt.

Ownership

Etruscan, through its wholly owned subsidiary Cayman Burkina Mines Ltd, holds a 90% interest in Burkina Mining Company (BMC) which has been granted the rights to exploit the Youga Gold Deposit. The remaining 10% of BMC is held by the Government of Burkina Faso.

Youga Resource and Reserve

The Youga Gold Deposit feasibility study completed January, 2005 by RSG Global (Pty) Ltd. and MDM Ferroman (Pty) Ltd. as updated October, 2006, concludes that Youga will produce an average of 88,000 ounces of gold per year over a 6.6 year mine life from five deposits.

The resource estimates (which include mineable reserves) at a 1.0 gram per tonne cutoff grade for the five zones ( A2 Main, A2 East, A2 West Zone- One, A2 West Zone-Two and A2 West Zone-Three) were prepared by RSG Global in accordance with National Instrument 43-101 and are summarized as follows:

Youga Mineral Resource
Measured Indicated Inferred
Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
4,077,000 3.1 g/t 415,000 5,238,000 2.3 g/t 378,000 1,734,000 1.7 g/t 94,000

Youga Mineral Reserves
Proven Probable Total
Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
4,000,000 3.1 g/t 388,000 2,700,000 2.3 g/t 193,000 6,600,000 2.7 g/t 580,000

The updated life-of-mine reserves at Youga as at December 31, 2008 calculated by the Company using a US$700 per ounce gold price are estimated at 6.8 million tonnes with an average grade of 2.7 grams per tonne containing 596,000 ounces of gold. In addition, 1.7 million tonnes have been classified as marginal ore with an average grade of 0.69 grams per tonne. This material will be stockpiled separately and considered for processing at the end of the mine life. This material had been classified as waste in the 2006 feasibility study reserve estimation.

Mine Development and Operations

Milling of ore at the Youga Gold Project commenced in February 2008 and commercial production and substantial completion of construction was effective July 1, 2008.

The initial mining operation is comprised of five pits with the ore being processed through a conventional gravity-CIL (carbon-in-leach) plant with a design capacity of one million tonnes per annum. The initial ore reserve is estimated at 6.6 million tonnes, allowing for a mine life of 6.6 years at the proposed processing rate. All of the ore and waste will be mined from the open pits using conventional mining equipment.

The treatment plant includes direct-dump ore receiving followed by three stages of crushing and one stage of milling. The ground ore is fed to a bank of cyclones where the over size is fed to the gravity circuit, consisting of a centrifugal concentrator and a shaking table. The under size is fed to the leaching circuit. A total of six tanks are being used to leach and recover the non-gravity recoverable gold on activated carbon. The gold is then extracted from the activated carbon and deposited using an electrowinning step. The recovered gold is heated in a smelting furnace and then poured into gold dore bars. Based on the Youga Feasibility Study test work, the overall gold recovery is anticipated to be in the range of 93 to 94%.

Drilling and blasting is required prior to mining. All of the pits contain hard-rock (ore and waste) material, and there are mineral free digging areas. Following blasting, the ore is excavated and transported by conventional mining gear. The primary fleet consists of a 120 tonne excavator and 100 tonne haul trucks. The drilling and blasting is being undertaken under contract with Nitrochimie SNC and the mining (load/haul) under contract with PW Mining International Limited.

The primary water supply for the plant is pumped from the nearby Nakambe River via an 11 kilometer pipeline to a raw water storage pond. The tailings area is designed to maximize water recovery in an effort to minimize the primary water demand.

Permanent power supply will be by way of grid power from the nearby Ghanaian national power grid operated by the Volta River Authority. A 21 kilometer powerline is being built from the town of Zebila in Ghana directly to site. The capacity of the line is designed for a minimum transmission of 10 MW. Full on site back up power generation capacity (8 mega watts) is provided via diesel generators. The diesel generators are presently being utilized until grid power is available and thereafter will ensure that milling operations continue uninterrupted should there be any periodic load shedding during the summer months. The power plant was supplied and commissioned by SDMO of France.

Employment on the Youga Gold Project during production is approximately 350 full time employees including both expatriate and local positions. There is a program of extensive training of the local work force for the management and skilled positions. In the longer term, it is anticipated that Burkina Faso nationals will fill the majority of the operating and management positions within BMC.

Economics and Financing


The total capital expenditure for the development of the Youga Gold Mine including preproduction and financing costs was $83.5 million. These costs were funded in part by a US$35 million senior debt facility and a US$7.5 million subordinated debt facility provided by RMB Australia Holdings Ltd. ("RMB") and Macquarie Bank Limited ("Macquarie"). The debt facilities were arranged by RMB Resources Limited of Australia. The senior debt facility is structured as a full recourse loan to the Company until economic and technical completion conditions have been satisfied, upon which the debt facility converts and becomes non-recourse to the Company and is secured by all of Etruscan's interests in the Youga Gold Project. Standard project finance security provisions apply. The loan is repayable on a quarterly basis over a 4-year term and bears interest at LIBOR plus 3% pre-completion and LIBOR plus 2.5% post completion. The facility was fully drawn down during 2007. Subsequent to November 30, 2007 the Company completed and drew down the US$7.5 million subordinated debt facility. The subordinated loan is repayable in two equal quarterly instalments following the repayment of the senior debt facility and bears interest at LIBOR plus 3.5%.

Initial draw down under the senior debt facility was subject to the Company satisfying a number of conditions precedent including the implementation of a gold price protection program. In January 2007, the Company implemented a gold price protection program for the Youga Gold Mine comprised of a combination of bought put options and sold call options whereby 100% of gold production for the first 60 months (456,102 ounces) is price protected at a minimum price of US$629 per ounce. The put options were funded by writing call options covering 246,296 ounces over the same 60 month duration having a strike price of US$700 per ounce. The fixed monthly ratio of call options to put options is 0.54 to 1 (246,296 ounces / 456,102 ounces) with the put option volumes matched to the production schedule in the October 2006 Youga Feasibility Study Update. The program requires no cash or other margin.

As a result of the extended construction schedule, primarily due to the exceptionally heavy rains during the July to September period, the Company elected to settle for cash certain delivery obligations under the $700 call options for the first six months of the program (September 2007 to February 2008). In 2007 the Company settled for cash, delivery obligations aggregating 10,554 ounces at a net cost of $630,000. In the first eight months of fiscal 2008, the Company settled for cash, additional delivery obligations aggregating 19,702 ounces at a net cost of $3.7 million. In the eight months ended November 30, 2008, the Company also delivered into the hedge obligation a total of 25,628 ounces from production.

Gold production for fiscal 2008 which comprises the five months of commercial production ended November 30th aggregated 29,305 ounces at an estimated cash operating cost of US$598 per ounce. A total of 371,000 tonnes of ore were milled during the period at an average mill feed grade of 2.93 grams per tonne. The mill throughput represented 89% of forecast as certain aspects of the operation continued to be optimized during the period.

Gold sales for the five month period aggregated 26,988 ounces which generated cash revenues of $22.3 million. A total of 19,022 ounces were delivered into the $700 per ounce hedge commitment and 7,966 ounces were sold at spot prices for an average realized gold price for the five month period of $746 per ounce.

Gold production for fiscal 2009 is estimated to be between 80,000 and 90,000 ounces.

Additional Exploration on the Youga Mining Permit


The Company has completed regional and detailed mapping as well as airborne and ground geophysics identifying a number of exploration targets within the Youga mining permit. The Company continues to evaluate near-surface mineralized zones that can provide additional mine reserves. Six potential satellite deposits are known to exist within a three kilometer radius of the Youga mill site: the Nanga Zone, the Leduc Zone, the A2 Village Zone, the Village Tail Zone, A2 West Zones 4 & 5, and the Zegoré Zone. In 2008, the Company completed sufficient work to release resource estimates on two of these zones in the mining permit as follows:

Zone
Cut-off
Indicated Resource
Inferred Resource
Name
Grade
Tonnes
Grade
Gold
Tonnes
Grade
Gold
(g/t)
(g/t)
(oz)
(g/t)
(oz)
Nanga
1.0
1,057,000
1.2
41,000
179,000
1.1
6,000
Tail
1.0
908,000
1.5
42,000
450,000
1.4
21,000
Total
1.0
1,964,000
1.3
83,000
629,000
1.2
27,000

Insufficient drilling has been carried out to categorize any of these resources as "measured". Additional drilling is planned on all zones to increase the confidence level of the resource categories.

Satellite Deposits and Strategic Land Package
Satellite Deposits and Strategic Land Package
click to enlarge

 

Show printable version of 'Youga Gold Mine - New' in a New Window
Email 'Youga Gold Mine - New' to a friend



© 2006 Etruscan Resources Inc. All Rights Reserved. | Disclaimer